Novarly ParcelRenewable sites

Renewable sitesCrystal Rig Wind Farm Phase 2a

Crystal Rig Wind Farm Phase 2a

Crystal Rig Wind Farm Phase 2a is operational in Scotland with a recorded capacity of 138 MW, and has been generating since 2010-10-25.

138 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-10-25
Wind Onshore
Technology
Fred Olsen Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted2007-07-17
Permission granted2008-07-30
12 months after submission
Operational2010-10-25
27 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Crystal Rig Wind Farm Phase IV
Wind Onshore · Under Construction
480.4 km
Aikengall II Community Wind Farm Battery
Battery · Operational
801.3 km
Crystal Rig Extension II
Wind Onshore · Operational
20.71.8 km
Crystal Rig Phase 1
Wind Onshore · Operational
62.52.3 km
Crystal Rig Wind Farm Phase III
Wind Onshore · Operational
13.83 km
Aikengall
Wind Onshore · Operational
483.1 km
Aikengall II, Wester Dod Community Wind Farm
Wind Onshore · Operational
60.83.1 km
Aikengall IIa Community Wind Farm
Wind Onshore · Operational
81.74.8 km

How big is Crystal Rig Wind Farm Phase 2a?

Crystal Rig Wind Farm Phase 2a has a recorded installed capacity of 138 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Crystal Rig Wind Farm Phase 2a?

REPD records the operator as Fred Olsen Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Crystal Rig Wind Farm Phase 2a approved and built?

The application was submitted on 2007-07-17. Permission was granted on 2008-07-30, 12 months later. The site became operational on 2010-10-25, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3440.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council