Renewable sites › Berthlwyd Farm
Berthlwyd Farm
Berthlwyd Farm is operational in Rhondda Cynon Taf with a recorded capacity of 5 MW, and has been generating since 2017-02-15.
Planning and build timeline
| Application submitted | 2015-06-01 |
| Permission granted | 2016-03-17 10 months after submission |
| Operational | 2017-02-15 11 months after consent |
Rhondda Cynon Taf’s record on solar
Rhondda Cynon Taf has decided 13 solar farms and approved 100%, taking a median of 5 months. See every solar farm decision in Rhondda Cynon Taf →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Maes Bach Farm Solar Photovoltaics · Operational | 4.9 | 3.6 km |
West of Rhiwfelin Fach Farm Wind Onshore · Operational | 1.5 | 4.9 km |
Energy Centre Royal Mint Battery · Operational | 20 | 5.1 km |
Coed Ely - Solar Farm Solar Photovoltaics · Under Construction | 6 | 6.3 km |
Graig Fatha Farm Wind Onshore · Operational | 2.5 | 7 km |
Mynydd Portref Wind Farm extension Wind Onshore · Operational | 12 | 8.5 km |
Agricultural Land at Trecastle Solar Photovoltaics · Operational | 4 | 9.3 km |
Taff Ely Wind Farm Wind Onshore · Operational | 9 | 9.3 km |
How big is Berthlwyd Farm?
Berthlwyd Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Berthlwyd Farm?
REPD records the operator as Greencoat Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Berthlwyd Farm approved and built?
The application was submitted on 2015-06-01. Permission was granted on 2016-03-17, 10 months later. The site became operational on 2017-02-15, 11 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5560.