Renewable sitesBerthlwyd Farm

Berthlwyd Farm

Berthlwyd Farm is an operational 5 MW solar farm in Rhondda Cynon Taf, generating since 15 February 2017. Planning permission was granted on 17 March 2016, 10 months after submission. Operator of record: Greencoat Capital.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 15 February 2017
Solar Photovoltaics
Technology
Greencoat Capital
Rhondda Cynon Taf
Authority
Wales

Planning and build timeline

Application submitted1 June 2015
Permission granted17 March 2016
10 months after submission
Operational15 February 2017
11 months after consent

Screening a site of your own?

RedlineUK · £39

Rhondda Cynon Taf approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Berthlwyd Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Rhondda Cynon Taf’s record on solar

Rhondda Cynon Taf has decided 13 solar farms and approved 100%, taking a median of 5 months. See every solar farm decision in Rhondda Cynon Taf

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.93.6 km
Wind Onshore · Operational
1.54.9 km
Battery · Operational
205.1 km
Solar Photovoltaics · Under Construction
66.3 km
Wind Onshore · Operational
2.57 km
Wind Onshore · Operational
128.5 km
Solar Photovoltaics · Operational
49.3 km
Wind Onshore · Operational
99.3 km

How big is Berthlwyd Farm?

Berthlwyd Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Berthlwyd Farm?

REPD records the operator as Greencoat Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Berthlwyd Farm approved and built?

The application was submitted on 1 June 2015. Permission was granted on 17 March 2016, 10 months later. The site became operational on 15 February 2017, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5560.

Novarly Parcel · official public data, read properly · parcel.novarly.com