Planning and build timeline

Application submitted2005-02-01
Permission granted2013-07-29
102 months after submission
Operational2017-01-13
42 months after consent

Derry City and Strabane’s record on onshore wind

Derry City and Strabane has decided 42 onshore wind schemes and approved 79%, taking a median of 29.1 months. See every onshore wind scheme decision in Derry City and Strabane

Other built sites within 15 km

SiteMWDistance
Townlands of Carrickatane
Wind Onshore · Operational
20.71.5 km
Slieve Kirk
Wind Onshore · Operational
27.66.3 km
Curryfree Wind Farm
Wind Onshore · Operational
158.3 km
Clondermot Turbines
Wind Onshore · Operational
4.611.3 km
Owenreagh Wind Farm
Wind Onshore · Operational
511.5 km
Owenreagh Extension
Wind Onshore · Operational
5.111.6 km
Monnaboy Wind Farm
Wind Onshore · Operational
1211.8 km
Tyrone Energy 1
Biomass (dedicated) · Operational
2.112.9 km

How big is Eglish Mountain?

Eglish Mountain has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Eglish Mountain?

REPD records the operator as ESB (Northern Wind Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Eglish Mountain approved and built?

The application was submitted on 2005-02-01. Permission was granted on 2013-07-29, 102 months later. The site became operational on 2017-01-13, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4264.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council