Renewable sites › Owenreagh Wind Farm
Owenreagh Wind Farm
Owenreagh Wind Farm is operational in Derry City and Strabane with a recorded capacity of 5 MW, and has been generating since 1997-01-01.
Planning and build timeline
| Application submitted | 1995-10-30 |
| Permission granted | 1996-04-04 5 months after submission |
| Operational | 1997-01-01 9 months after consent |
Derry City and Strabane’s record on onshore wind
Derry City and Strabane has decided 42 onshore wind schemes and approved 79%, taking a median of 29.1 months. See every onshore wind scheme decision in Derry City and Strabane →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Owenreagh Extension Wind Onshore · Operational | 5.1 | 0.5 km |
Tyrone Energy 1 Biomass (dedicated) · Operational | 2.1 | 6.4 km |
Eglish Mountain Wind Onshore · Operational | 13.8 | 11.5 km |
Slieve Kirk Wind Onshore · Operational | 27.6 | 12.7 km |
Bessy Bell Extension Wind Onshore · Operational | 9 | 12.9 km |
Townlands of Carrickatane Wind Onshore · Operational | 20.7 | 13 km |
Curryfree Wind Farm Wind Onshore · Operational | 15 | 13.4 km |
Bessy Bell Wind Farm Wind Onshore · Operational | 5 | 13.5 km |
How big is Owenreagh Wind Farm?
Owenreagh Wind Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Owenreagh Wind Farm?
REPD records the operator as EF Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Owenreagh Wind Farm approved and built?
The application was submitted on 1995-10-30. Permission was granted on 1996-04-04, 5 months later. The site became operational on 1997-01-01, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3118.