Monnaboy Wind Farm

Monnaboy Wind Farm is operational in Derry City and Strabane with a recorded capacity of 12 MW, and has been generating since 2015-11-15.

12 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-11-15
Wind Onshore
Technology
Gaelectric Developments/ CGN Europe Energy
Derry City and Strabane
Authority
Northern Ireland

Planning and build timeline

Application submitted2009-11-06
Permission granted2012-10-12
35 months after submission
Operational2015-11-15
37 months after consent

Derry City and Strabane’s record on onshore wind

Derry City and Strabane has decided 42 onshore wind schemes and approved 79%, taking a median of 29.1 months. See every onshore wind scheme decision in Derry City and Strabane

Other built sites within 15 km

SiteMWDistance
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2)
Wind Onshore · Operational
27.66.4 km
Altahullion
Wind Onshore · Operational
266.7 km
Slieve Kirk (formerly Glenconway)
Wind Onshore · Operational
18.46.7 km
Altahullion Phase II
Wind Onshore · Operational
11.78.7 km
Evermore Renewable Energy (CHP) / Lisahally Power Station
Biomass (dedicated) · Operational
159.7 km
Townlands of Carrickatane
Wind Onshore · Operational
20.710.3 km
Clondermot Turbines
Wind Onshore · Operational
4.611.5 km
Eglish Mountain
Wind Onshore · Operational
13.811.8 km

How big is Monnaboy Wind Farm?

Monnaboy Wind Farm has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Monnaboy Wind Farm?

REPD records the operator as Gaelectric Developments/ CGN Europe Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Monnaboy Wind Farm approved and built?

The application was submitted on 2009-11-06. Permission was granted on 2012-10-12, 35 months later. The site became operational on 2015-11-15, 37 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4155.