Renewable sites › Tyrone Energy 1
Tyrone Energy 1
Tyrone Energy 1 is an operational 2.1 MW biomass plant in Derry City and Strabane, generating since 6 August 2012. Planning permission was granted on 8 December 2009, 10 months after submission. Operator of record: Private Developer.
Planning and build timeline
| Application submitted | 3 February 2009 |
| Permission granted | 8 December 2009 10 months after submission |
| Operational | 6 August 2012 32 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Derry City and Strabane: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Tyrone Energy 1’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 5 | 6.4 km |
Wind Onshore · Operational | 5.1 | 6.9 km |
Wind Onshore · Operational | 15 | 10.3 km |
Wind Onshore · Operational | 27.6 | 10.7 km |
Wind Onshore · Operational | 13.8 | 12.9 km |
Wind Onshore · Operational | 20.7 | 14.1 km |
Wind Onshore · Operational | 4.6 | 14.2 km |
How big is Tyrone Energy 1?
Tyrone Energy 1 has a recorded installed capacity of 2.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tyrone Energy 1?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tyrone Energy 1 approved and built?
The application was submitted on 3 February 2009. Permission was granted on 8 December 2009, 10 months later. The site became operational on 6 August 2012, 32 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 122.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode