Renewable sitesClondermot Turbines

Clondermot Turbines

Clondermot Turbines is operational in Derry City and Strabane with a recorded capacity of 4.6 MW, and has been generating since 2015-04-14.

4.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-04-14
Wind Onshore
Technology
Energia Renewables
Derry City and Strabane
Authority
Northern Ireland

Planning and build timeline

Application submitted2007-02-21
Permission granted2010-01-18
35 months after submission
Operational2015-04-14
63 months after consent

Derry City and Strabane’s record on onshore wind

Derry City and Strabane has decided 42 onshore wind schemes and approved 79%, taking a median of 29.1 months. See every onshore wind scheme decision in Derry City and Strabane

Other built sites within 15 km

SiteMWDistance
Curryfree Wind Farm
Wind Onshore · Operational
154.3 km
Slieve Kirk
Wind Onshore · Operational
27.65.5 km
Evermore Renewable Energy (CHP) / Lisahally Power Station
Biomass (dedicated) · Operational
158.4 km
Townlands of Carrickatane
Wind Onshore · Operational
20.710.9 km
Eglish Mountain
Wind Onshore · Operational
13.811.3 km
Monnaboy Wind Farm
Wind Onshore · Operational
1211.5 km
Tyrone Energy 1
Biomass (dedicated) · Operational
2.114.2 km

How big is Clondermot Turbines?

Clondermot Turbines has a recorded installed capacity of 4.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clondermot Turbines?

REPD records the operator as Energia Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clondermot Turbines approved and built?

The application was submitted on 2007-02-21. Permission was granted on 2010-01-18, 35 months later. The site became operational on 2015-04-14, 63 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3877.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council