Myreton Crossroads

Myreton Crossroads is an operational 1.6 MW onshore wind farm in Moray, generating since 5 July 2013. Planning permission was granted on 19 July 2010, 17 months after submission. Operator of record: Seren Energy.

1.6 MW
Capacity
as recorded in REPD
Operational
Status
since 5 July 2013
Wind Onshore
Technology
Seren Energy
Moray
Authority
Scotland

Planning and build timeline

Application submitted9 February 2009
Permission granted19 July 2010
17 months after submission
Operational5 July 2013
36 months after consent

Screening a site of your own?

RedlineUK · £39

Moray approves 77% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Myreton Crossroads’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Moray’s record on onshore wind

Moray has decided 13 onshore wind schemes and approved 77%, taking a median of 16.4 months. See every onshore wind scheme decision in Moray

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
4.60.9 km
Wind Onshore · Operational
4.67.2 km
Battery · Under Construction
30011 km
Wind Onshore · Operational
2.411.9 km
Anaerobic Digestion · Under Construction
12.6 km
Wind Onshore · Operational
1812.6 km
Wind Onshore · Operational
2.313.3 km
Wind Onshore · Operational
2.313.6 km

How big is Myreton Crossroads?

Myreton Crossroads has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Myreton Crossroads?

REPD records the operator as Seren Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Myreton Crossroads approved and built?

The application was submitted on 9 February 2009. Permission was granted on 19 July 2010, 17 months later. The site became operational on 5 July 2013, 36 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3804.