Renewable sites › Dunsland Cross Wind Farm
Dunsland Cross Wind Farm
Dunsland Cross Wind Farm is an operational 7.5 MW onshore wind farm in Torridge, generating since 8 March 2017. Planning permission was granted on 22 January 2013, 12 months after submission. Operator of record: Temporis Capital.
Planning and build timeline
| Application submitted | 13 January 2012 |
| Permission granted | 22 January 2013 12 months after submission |
| Operational | 8 March 2017 49 months after consent |
Screening a site of your own?
Torridge approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Dunsland Cross Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Torridge’s record on onshore wind
Torridge has decided 8 onshore wind schemes and approved 63%, taking a median of 18.3 months. See every onshore wind scheme decision in Torridge →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 2.5 km |
Solar Photovoltaics · Operational | 1 | 6.3 km |
Solar Photovoltaics · Operational | 5 | 6.6 km |
Solar Photovoltaics · Operational | 3.6 | 6.6 km |
Anaerobic Digestion · Operational | 1.4 | 6.9 km |
Solar Photovoltaics · Operational | 11.8 | 7.6 km |
Solar Photovoltaics · Operational | 3 | 8.3 km |
Wind Onshore · Operational | 1.5 | 8.9 km |
How big is Dunsland Cross Wind Farm?
Dunsland Cross Wind Farm has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dunsland Cross Wind Farm?
REPD records the operator as Temporis Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dunsland Cross Wind Farm approved and built?
The application was submitted on 13 January 2012. Permission was granted on 22 January 2013, 12 months later. The site became operational on 8 March 2017, 49 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4227.