Dunsland Cross Wind Farm

Dunsland Cross Wind Farm is an operational 7.5 MW onshore wind farm in Torridge, generating since 8 March 2017. Planning permission was granted on 22 January 2013, 12 months after submission. Operator of record: Temporis Capital.

7.5 MW
Capacity
as recorded in REPD
Operational
Status
since 8 March 2017
Wind Onshore
Technology
Temporis Capital
Torridge
Authority
England

Planning and build timeline

Application submitted13 January 2012
Permission granted22 January 2013
12 months after submission
Operational8 March 2017
49 months after consent

Screening a site of your own?

RedlineUK · £39

Torridge approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dunsland Cross Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Torridge’s record on onshore wind

Torridge has decided 8 onshore wind schemes and approved 63%, taking a median of 18.3 months. See every onshore wind scheme decision in Torridge

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
52.5 km
Solar Photovoltaics · Operational
16.3 km
Solar Photovoltaics · Operational
56.6 km
Solar Photovoltaics · Operational
3.66.6 km
Anaerobic Digestion · Operational
1.46.9 km
Solar Photovoltaics · Operational
11.87.6 km
Solar Photovoltaics · Operational
38.3 km
Wind Onshore · Operational
1.58.9 km

How big is Dunsland Cross Wind Farm?

Dunsland Cross Wind Farm has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dunsland Cross Wind Farm?

REPD records the operator as Temporis Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dunsland Cross Wind Farm approved and built?

The application was submitted on 13 January 2012. Permission was granted on 22 January 2013, 12 months later. The site became operational on 8 March 2017, 49 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4227.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode