Dunsland Cross Wind Farm

Dunsland Cross Wind Farm is operational in Torridge with a recorded capacity of 7.5 MW, and has been generating since 2017-03-08.

7.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-08
Wind Onshore
Technology
Temporis Capital
Torridge
Authority
England

Planning and build timeline

Application submitted2012-01-13
Permission granted2013-01-22
12 months after submission
Operational2017-03-08
49 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Torridge’s record on onshore wind

Torridge has decided 8 onshore wind schemes and approved 63%, taking a median of 18.3 months. See every onshore wind scheme decision in Torridge

Other built sites within 15 km

SiteMWDistance
Foxcombe Farm Solar Park
Solar Photovoltaics · Operational
52.5 km
Whiddon Farm
Solar Photovoltaics · Operational
16.3 km
West Venn Solar Farm
Solar Photovoltaics · Operational
56.6 km
EASTACOMBE SOLAR FARM
Solar Photovoltaics · Operational
3.66.6 km
North Tamar Environ Project - Holsworthy (Farm AD)
Anaerobic Digestion · Operational
1.46.9 km
Derriton Fields Solar Farm
Solar Photovoltaics · Operational
11.87.6 km
Great Knowle Farm Solar
Solar Photovoltaics · Operational
38.3 km
Nethercott Farm
Wind Onshore · Operational
1.58.9 km

How big is Dunsland Cross Wind Farm?

Dunsland Cross Wind Farm has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dunsland Cross Wind Farm?

REPD records the operator as Temporis Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dunsland Cross Wind Farm approved and built?

The application was submitted on 2012-01-13. Permission was granted on 2013-01-22, 12 months later. The site became operational on 2017-03-08, 49 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4227.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council