Renewable sites › Nethercott Farm
Nethercott Farm
Nethercott Farm is operational in Torridge with a recorded capacity of 1.5 MW, and has been generating since 2016-12-15.
Planning and build timeline
| Application submitted | 2014-01-15 |
| Permission granted | 2014-07-03 6 months after submission |
| Operational | 2016-12-15 29 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Torridge’s record on onshore wind
Torridge has decided 8 onshore wind schemes and approved 63%, taking a median of 18.3 months. See every onshore wind scheme decision in Torridge →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
West Venn Solar Farm Solar Photovoltaics · Operational | 5 | 2.8 km |
EASTACOMBE SOLAR FARM Solar Photovoltaics · Operational | 3.6 | 3.2 km |
Whiddon Farm Solar Photovoltaics · Operational | 1 | 4.2 km |
West Ditchen Farm Solar Photovoltaics · Operational | 5 | 5.4 km |
Parabel North Beer Solar Farm Solar Photovoltaics · Operational | 6.8 | 6.7 km |
Land West of Parsonage Wood Solar Photovoltaics · Operational | 4.2 | 6.8 km |
Derriton Fields Solar Farm Solar Photovoltaics · Operational | 11.8 | 6.9 km |
CRINACOTT SOLAR FARM (Pyworthy) Solar Photovoltaics · Operational | 6.7 | 6.9 km |
How big is Nethercott Farm?
Nethercott Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Nethercott Farm?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Nethercott Farm approved and built?
The application was submitted on 2014-01-15. Permission was granted on 2014-07-03, 6 months later. The site became operational on 2016-12-15, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3368.