Dunsfold Park Solar Farm
Dunsfold Park Solar Farm is operational in Waverley with a recorded capacity of 2 MW, and has been generating since 2011-07-26.
Planning and build timeline
| Application submitted | 2010-11-03 |
| Permission granted | 2011-03-30 5 months after submission |
| Operational | 2011-07-26 4 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Waverley’s record on solar
Waverley has decided 6 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in Waverley →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Five Oaks Solar Farm Solar Photovoltaics · Operational | 5 | 9.6 km |
Land at Five Oaks Farm Solar Photovoltaics · Operational | 5 | 11.2 km |
Albury Landfill Landfill Gas · Operational | 1.5 | 12.3 km |
Broockhurst Wood Landfill Gas · Operational | 2 | 13.9 km |
Royal Surrey County Hospital - Solar Panels Solar Photovoltaics · Under Construction | — | 14.2 km |
How big is Dunsfold Park Solar Farm?
Dunsfold Park Solar Farm has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dunsfold Park Solar Farm?
REPD records the operator as Dunsfold Park Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dunsfold Park Solar Farm approved and built?
The application was submitted on 2010-11-03. Permission was granted on 2011-03-30, 5 months later. The site became operational on 2011-07-26, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1084.