Novarly ParcelRenewable sites

Renewable sitesBankend Rig

Bankend Rig

Bankend Rig is an operational 14.3 MW onshore wind farm in South Lanarkshire, generating since 27 March 2013. Planning permission was granted on 16 June 2011, 60 months after submission. Operator of record: I & H Brown Ltd.

14.3 MW
Capacity
as recorded in REPD
Operational
Status
since 27 March 2013
Wind Onshore
Technology
I & H Brown Ltd
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted16 June 2006
Permission granted16 June 2011
60 months after submission
Operational27 March 2013
21 months after consent

Screening a site of your own?

RedlineUK · £39

South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bankend Rig’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Under Construction
363.2 km
Wind Onshore · Operational
29.94.1 km
Wind Onshore · Operational
288.2 km
Wind Onshore · Operational
88.48.7 km
Wind Onshore · Operational
67.28.7 km
Wind Onshore · Operational
3010.2 km
Wind Onshore · Operational
3610.7 km
Wind Onshore · Operational
6610.9 km

How big is Bankend Rig?

Bankend Rig has a recorded installed capacity of 14.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bankend Rig?

REPD records the operator as I & H Brown Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bankend Rig approved and built?

The application was submitted on 16 June 2006. Permission was granted on 16 June 2011, 60 months later. The site became operational on 27 March 2013, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4055.