Renewable sitesDerehams Farm, Derehams Lane - Battery Storage

Derehams Farm, Derehams Lane - Battery Storage

Derehams Farm, Derehams Lane - Battery Storage is an operational 40 MW battery storage site in Buckinghamshire, generating since 6 August 2025. Planning permission was granted on 29 June 2023, 7 months after submission. Operator of record: Eku Energy / Statkraft.

40 MW
Capacity
as recorded in REPD
Operational
Status
since 6 August 2025
Battery
Technology
Eku Energy / Statkraft
Buckinghamshire
Authority
England

Planning and build timeline

Application submitted14 November 2022
Permission granted29 June 2023
7 months after submission
Operational6 August 2025
25 months after consent

Screening a site of your own?

RedlineUK · £39

Buckinghamshire approves 82% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Derehams Farm, Derehams Lane - Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Buckinghamshire’s record on battery storage

Buckinghamshire has decided 11 battery storage schemes and approved 82%, taking a median of 9 months. See every battery storage scheme decision in Buckinghamshire

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
7.57.2 km
Landfill Gas · Operational
17.2 km
Landfill Gas · Operational
17.2 km
Landfill Gas · Operational
1.97.3 km
Solar Photovoltaics · Operational
0.299.5 km
Landfill Gas · Operational
1.410 km
EfW Incineration · Operational
5010.7 km
EfW Incineration · Under Construction
49.910.8 km

How big is Derehams Farm, Derehams Lane - Battery Storage?

Derehams Farm, Derehams Lane - Battery Storage has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Derehams Farm, Derehams Lane - Battery Storage?

REPD records the operator as Eku Energy / Statkraft. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Derehams Farm, Derehams Lane - Battery Storage approved and built?

The application was submitted on 14 November 2022. Permission was granted on 29 June 2023, 7 months later. The site became operational on 6 August 2025, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12803.