Springfield Farm
Springfield Farm is operational in Buckinghamshire with a recorded capacity of 1.4 MW, and has been generating since 2006-09-01.
Planning and build timeline
| Application submitted | 2006-03-16 |
| Permission granted | 2006-05-23 2 months after submission |
| Operational | 2006-09-01 3 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Conservation area — Gerrards Cross Common
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wapsey's Wood III Landfill Gas · Operational | 1 | 2.7 km |
Wapsey's Wood II Landfill Site Landfill Gas · Operational | 1 | 2.8 km |
Wapsey's Wood Landfill Gas · Operational | 7.5 | 2.8 km |
Fibrepower, Slough EfW Incineration · Operational | 50 | 8.1 km |
Slough Heat & Power Station EfW Incineration · Under Construction | 49.9 | 8.1 km |
Mount Vernon Hospital - Solar Panels Solar Photovoltaics · Operational | — | 8.5 km |
Derehams Farm, Derehams Lane - Battery Storage Battery · Operational | 40 | 10 km |
Slough Sewage Treatment Works Sewage Sludge Digestion · Operational | 1.2 | 10.1 km |
How big is Springfield Farm?
Springfield Farm has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Springfield Farm?
REPD records the operator as ONYX. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Springfield Farm approved and built?
The application was submitted on 2006-03-16. Permission was granted on 2006-05-23, 2 months later. The site became operational on 2006-09-01, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 640.