Renewable sitesFibrepower, Slough

Fibrepower, Slough

Fibrepower, Slough is operational in Slough with a recorded capacity of 50 MW, and has been generating since 2002-05-01.

50 MW
Capacity
as recorded in REPD
Operational
Status
since 2002-05-01
EfW Incineration
Technology
Scottish and Southern Energy (SSE)
Slough
Authority
England

Planning and build timeline

Application submitted1994-09-23
Permission granted1999-03-29
54 months after submission
Operational2002-05-01
37 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Slough Heat & Power Station
EfW Incineration · Under Construction
49.90.1 km
Slough Sewage Treatment Works
Sewage Sludge Digestion · Operational
1.22.1 km
Iomart, Clivemont Road - Solar Panels
Solar Photovoltaics · Operational
0.296.8 km
Wapsey's Wood III
Landfill Gas · Operational
17.6 km
Wapsey's Wood
Landfill Gas · Operational
7.57.6 km
Wapsey's Wood II Landfill Site
Landfill Gas · Operational
17.7 km
Colnbrook Landfill
Landfill Gas · Operational
1.98 km
Springfield Farm
Landfill Gas · Operational
1.48.1 km

How big is Fibrepower, Slough?

Fibrepower, Slough has a recorded installed capacity of 50 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fibrepower, Slough?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fibrepower, Slough approved and built?

The application was submitted on 1994-09-23. Permission was granted on 1999-03-29, 54 months later. The site became operational on 2002-05-01, 37 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 831.