Novarly ParcelRenewable sites

Renewable sitesDalby

Dalby

Dalby is operational in Melton with a recorded capacity of 7.2 MW, and has been generating since 2016-03-15.

7.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-15
Wind Onshore
Technology
Ecotricity
Melton
Authority
England

Planning and build timeline

Application submitted2010-05-19
Permission granted2010-12-17
7 months after submission
Operational2016-03-15
63 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Six Hills Solar Farm
Solar Photovoltaics · Operational
18.72.9 km
GDL Wymeswold Solar Farm/land off the A6006
Solar Photovoltaics · Operational
6.13.6 km
The Sawmill
Biomass (dedicated) · Operational
6.83.8 km
Wymeswold Airfield
Solar Photovoltaics · Operational
345.2 km
Land to the East of Burton Lane
Solar Photovoltaics · Operational
2.65.2 km
Land to the west of Ashfordby Business Park
Solar Photovoltaics · Operational
3.57.2 km
Asfordby Business Park (1)
Battery · Operational
23.48 km
British Geological, Keywork Solar Panels
Solar Photovoltaics · Under Construction
0.628.6 km

How big is Dalby?

Dalby has a recorded installed capacity of 7.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dalby?

REPD records the operator as Ecotricity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dalby approved and built?

The application was submitted on 2010-05-19. Permission was granted on 2010-12-17, 7 months later. The site became operational on 2016-03-15, 63 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3764.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council