Novarly ParcelRenewable sites

Renewable sitesLand to the west of Ashfordby Business Park

Land to the west of Ashfordby Business Park

Land to the west of Ashfordby Business Park is an operational 3.5 MW solar farm in Melton, generating since 26 April 2016. Planning permission was granted on 10 September 2015, 3 months after submission. Operator of record: First Renewable Developments.

3.5 MW
Capacity
as recorded in REPD
Operational
Status
since 26 April 2016
Solar Photovoltaics
Technology
First Renewable Developments
Melton
Authority
England

Planning and build timeline

Application submitted11 June 2015
Permission granted10 September 2015
3 months after submission
Operational26 April 2016
8 months after consent

Screening a site of your own?

RedlineUK · £39

Melton approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land to the west of Ashfordby Business Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Melton’s record on solar

Melton has decided 12 solar farms and approved 100%, taking a median of 3.2 months. See every solar farm decision in Melton

Other built sites within 15 km

SiteMWDistance
Battery · Operational
23.40.9 km
Solar Photovoltaics · Operational
18.76 km
Wind Onshore · Operational
7.27.2 km
Biomass (dedicated) · Operational
6.89.4 km
Solar Photovoltaics · Operational
6.110.7 km
Solar Photovoltaics · Operational
3412 km
Solar Photovoltaics · Operational
2.612 km
Solar Photovoltaics · Operational
512.8 km

How big is Land to the west of Ashfordby Business Park?

Land to the west of Ashfordby Business Park has a recorded installed capacity of 3.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land to the west of Ashfordby Business Park?

REPD records the operator as First Renewable Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land to the west of Ashfordby Business Park approved and built?

The application was submitted on 11 June 2015. Permission was granted on 10 September 2015, 3 months later. The site became operational on 26 April 2016, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5478.