Asfordby Business Park (1) is an operational 23.4 MW battery storage site in Melton, generating since 1 April 2019. Planning permission was granted on 30 September 2016, 2 months after submission. Operator of record: UK Power Reserve.

23.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 2019
Battery
Technology
UK Power Reserve
Melton
Authority
England

Planning and build timeline

Application submitted1 August 2016
Permission granted30 September 2016
2 months after submission
Operational1 April 2019
30 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Melton: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Asfordby Business Park (1)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
3.50.9 km
Solar Photovoltaics · Operational
18.76.9 km
Wind Onshore · Operational
7.28 km
Biomass (dedicated) · Operational
6.810 km
Solar Photovoltaics · Operational
6.111.5 km
Solar Photovoltaics · Operational
3412.9 km
Solar Photovoltaics · Operational
2.612.9 km
Solar Photovoltaics · Operational
513.7 km

How big is Asfordby Business Park (1)?

Asfordby Business Park (1) has a recorded installed capacity of 23.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Asfordby Business Park (1)?

REPD records the operator as UK Power Reserve. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Asfordby Business Park (1) approved and built?

The application was submitted on 1 August 2016. Permission was granted on 30 September 2016, 2 months later. The site became operational on 1 April 2019, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6932.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode