Land to the East of Burton Lane is an operational 2.6 MW solar farm in Charnwood, generating since 15 March 2016. Planning permission was granted on 21 September 2015, 11 months after submission. Operator of record: EBS Energy LLP.
Planning and build timeline
| Application submitted | 17 October 2014 |
| Permission granted | 21 September 2015 11 months after submission |
| Operational | 15 March 2016 6 months after consent |
Screening a site of your own?
Charnwood approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land to the East of Burton Lane’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Charnwood’s record on solar
Charnwood has decided 18 solar farms and approved 94%, taking a median of 5.5 months. See every solar farm decision in Charnwood →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 34 | 0 km |
Solar Photovoltaics · Operational | 6.1 | 1.8 km |
Wind Onshore · Operational | 7.2 | 5.2 km |
Solar Photovoltaics · Operational | 18.7 | 6.3 km |
Biomass (dedicated) · Operational | 6.8 | 6.7 km |
Solar Photovoltaics · Operational | 5 | 7.1 km |
Solar Photovoltaics · Under Construction | 0.62 | 8.7 km |
Landfill Gas · Operational | 1.6 | 8.7 km |
How big is Land to the East of Burton Lane?
Land to the East of Burton Lane has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land to the East of Burton Lane?
REPD records the operator as EBS Energy LLP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land to the East of Burton Lane approved and built?
The application was submitted on 17 October 2014. Permission was granted on 21 September 2015, 11 months later. The site became operational on 15 March 2016, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1285.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode