Land to the East of Burton Lane is operational in Charnwood with a recorded capacity of 2.6 MW, and has been generating since 2016-03-15.

2.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-15
Solar Photovoltaics
Technology
EBS Energy LLP
Charnwood
Authority
England

Planning and build timeline

Application submitted2014-10-17
Permission granted2015-09-21
11 months after submission
Operational2016-03-15
6 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Charnwood’s record on solar

Charnwood has decided 18 solar farms and approved 94%, taking a median of 5.5 months. See every solar farm decision in Charnwood

Other built sites within 15 km

SiteMWDistance
Wymeswold Airfield
Solar Photovoltaics · Operational
340 km
GDL Wymeswold Solar Farm/land off the A6006
Solar Photovoltaics · Operational
6.11.8 km
Dalby
Wind Onshore · Operational
7.25.2 km
Six Hills Solar Farm
Solar Photovoltaics · Operational
18.76.3 km
The Sawmill
Biomass (dedicated) · Operational
6.86.7 km
Gypsom Solar Farm
Solar Photovoltaics · Operational
57.1 km
British Geological, Keywork Solar Panels
Solar Photovoltaics · Under Construction
0.628.7 km
Mountsorrel Landfill Site
Landfill Gas · Operational
1.68.7 km

How big is Land to the East of Burton Lane?

Land to the East of Burton Lane has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land to the East of Burton Lane?

REPD records the operator as EBS Energy LLP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land to the East of Burton Lane approved and built?

The application was submitted on 2014-10-17. Permission was granted on 2015-09-21, 11 months later. The site became operational on 2016-03-15, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1285.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council