Crystal Rig Wind Farm Phase III

Crystal Rig Wind Farm Phase III is operational in Scotland with a recorded capacity of 13.8 MW, and has been generating since 2016-12-22.

13.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-12-22
Wind Onshore
Technology
Fred Olsen Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted2013-06-14
Permission granted2015-06-18
24 months after submission
Operational2016-12-22
18 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Crystal Rig Extension II
Wind Onshore · Operational
20.71.7 km
Aikengall II Community Wind Farm Battery
Battery · Operational
802.5 km
Crystal Rig Wind Farm Phase IV
Wind Onshore · Under Construction
482.6 km
Aikengall
Wind Onshore · Operational
483 km
Aikengall II, Wester Dod Community Wind Farm
Wind Onshore · Operational
60.83 km
Crystal Rig Wind Farm Phase 2a
Wind Onshore · Operational
1383 km
Crystal Rig Phase 1
Wind Onshore · Operational
62.55.1 km
Aikengall IIa Community Wind Farm
Wind Onshore · Operational
81.76.3 km

How big is Crystal Rig Wind Farm Phase III?

Crystal Rig Wind Farm Phase III has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Crystal Rig Wind Farm Phase III?

REPD records the operator as Fred Olsen Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Crystal Rig Wind Farm Phase III approved and built?

The application was submitted on 2013-06-14. Permission was granted on 2015-06-18, 24 months later. The site became operational on 2016-12-22, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4215.