Renewable sites › Crystal Rig Extension II
Crystal Rig Extension II
Crystal Rig Extension II is operational in Scotland with a recorded capacity of 20.7 MW, and has been generating since 2010-10-25.
Planning and build timeline
| Application submitted | 2004-05-01 |
| Permission granted | 2005-05-25 13 months after submission |
| Operational | 2010-10-25 65 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crystal Rig Wind Farm Phase IV Wind Onshore · Under Construction | 48 | 1.6 km |
Crystal Rig Wind Farm Phase III Wind Onshore · Operational | 13.8 | 1.7 km |
Crystal Rig Wind Farm Phase 2a Wind Onshore · Operational | 138 | 1.8 km |
Aikengall II Community Wind Farm Battery Battery · Operational | 80 | 2.1 km |
Aikengall Wind Onshore · Operational | 48 | 3.5 km |
Aikengall II, Wester Dod Community Wind Farm Wind Onshore · Operational | 60.8 | 3.5 km |
Crystal Rig Phase 1 Wind Onshore · Operational | 62.5 | 4.1 km |
Aikengall IIa Community Wind Farm Wind Onshore · Operational | 81.7 | 6.2 km |
How big is Crystal Rig Extension II?
Crystal Rig Extension II has a recorded installed capacity of 20.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Crystal Rig Extension II?
REPD records the operator as Natural Power Consultants. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Crystal Rig Extension II approved and built?
The application was submitted on 2004-05-01. Permission was granted on 2005-05-25, 13 months later. The site became operational on 2010-10-25, 65 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3536.