Crystal Rig Extension II

Crystal Rig Extension II is operational in Scotland with a recorded capacity of 20.7 MW, and has been generating since 2010-10-25.

20.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-10-25
Wind Onshore
Technology
Natural Power Consultants
National
Authority
Scotland

Planning and build timeline

Application submitted2004-05-01
Permission granted2005-05-25
13 months after submission
Operational2010-10-25
65 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Crystal Rig Wind Farm Phase IV
Wind Onshore · Under Construction
481.6 km
Crystal Rig Wind Farm Phase III
Wind Onshore · Operational
13.81.7 km
Crystal Rig Wind Farm Phase 2a
Wind Onshore · Operational
1381.8 km
Aikengall II Community Wind Farm Battery
Battery · Operational
802.1 km
Aikengall
Wind Onshore · Operational
483.5 km
Aikengall II, Wester Dod Community Wind Farm
Wind Onshore · Operational
60.83.5 km
Crystal Rig Phase 1
Wind Onshore · Operational
62.54.1 km
Aikengall IIa Community Wind Farm
Wind Onshore · Operational
81.76.2 km

How big is Crystal Rig Extension II?

Crystal Rig Extension II has a recorded installed capacity of 20.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Crystal Rig Extension II?

REPD records the operator as Natural Power Consultants. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Crystal Rig Extension II approved and built?

The application was submitted on 2004-05-01. Permission was granted on 2005-05-25, 13 months later. The site became operational on 2010-10-25, 65 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3536.