Renewable sites › Aikengall
Aikengall
Aikengall is an operational 48 MW onshore wind farm in East Lothian, generating since 1 November 2008. Planning permission was granted on 16 March 2007, 25 months after submission. Operator of record: Community Wind Power.
Planning and build timeline
| Application submitted | 24 February 2005 |
| Permission granted | 16 March 2007 25 months after submission |
| Operational | 1 November 2008 20 months after consent |
Screening a site of your own?
East Lothian approves 100% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Aikengall’s recorded coordinate — swap in your own postcode or coordinates.
East Lothian’s record on onshore wind
East Lothian has decided 5 onshore wind schemes and approved 100%, taking a median of 10.6 months. See every onshore wind scheme decision in East Lothian →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 60.8 | 0 km |
Battery · Operational | 80 | 1.8 km |
Wind Onshore · Under Construction | 48 | 2.8 km |
Wind Onshore · Operational | 13.8 | 3 km |
Wind Onshore · Operational | 138 | 3.1 km |
Wind Onshore · Operational | 20.7 | 3.5 km |
Wind Onshore · Operational | 81.7 | 3.5 km |
Wind Onshore · Operational | 62.5 | 4 km |
How big is Aikengall?
Aikengall has a recorded installed capacity of 48 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Aikengall?
REPD records the operator as Community Wind Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Aikengall approved and built?
The application was submitted on 24 February 2005. Permission was granted on 16 March 2007, 25 months later. The site became operational on 1 November 2008, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4526.
Novarly Parcel · official public data, read properly · parcel.novarly.com