Renewable sites › Aikengall II, Wester Dod Community Wind Farm
Aikengall II, Wester Dod Community Wind Farm
Aikengall II, Wester Dod Community Wind Farm is operational in Scotland with a recorded capacity of 60.8 MW, and has been generating since 2017-11-15.
Planning and build timeline
| Application submitted | 2009-09-02 |
| Permission granted | 2013-03-01 42 months after submission |
| Operational | 2017-11-15 57 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Aikengall Wind Onshore · Operational | 48 | 0 km |
Aikengall II Community Wind Farm Battery Battery · Operational | 80 | 1.8 km |
Crystal Rig Wind Farm Phase IV Wind Onshore · Under Construction | 48 | 2.8 km |
Crystal Rig Wind Farm Phase III Wind Onshore · Operational | 13.8 | 3 km |
Crystal Rig Wind Farm Phase 2a Wind Onshore · Operational | 138 | 3.1 km |
Crystal Rig Extension II Wind Onshore · Operational | 20.7 | 3.5 km |
Aikengall IIa Community Wind Farm Wind Onshore · Operational | 81.7 | 3.5 km |
Crystal Rig Phase 1 Wind Onshore · Operational | 62.5 | 4 km |
How big is Aikengall II, Wester Dod Community Wind Farm?
Aikengall II, Wester Dod Community Wind Farm has a recorded installed capacity of 60.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Aikengall II, Wester Dod Community Wind Farm?
REPD records the operator as Community Windpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Aikengall II, Wester Dod Community Wind Farm approved and built?
The application was submitted on 2009-09-02. Permission was granted on 2013-03-01, 42 months later. The site became operational on 2017-11-15, 57 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4332.