Aikengall II Community Wind Farm Battery is operational in Scottish Borders with a recorded capacity of 80 MW, and has been generating since 2021-06-01.

80 MW
Capacity
as recorded in REPD
Operational
Status
since 2021-06-01
Battery
Technology
Community Wind Power
Scottish Borders
Authority
Scotland

Planning and build timeline

Application submitted2018-01-10
Permission granted2019-01-25
12 months after submission
Operational2021-06-01
28 months after consent

Other built sites within 15 km

SiteMWDistance
Crystal Rig Wind Farm Phase IV
Wind Onshore · Under Construction
481 km
Crystal Rig Wind Farm Phase 2a
Wind Onshore · Operational
1381.3 km
Aikengall II, Wester Dod Community Wind Farm
Wind Onshore · Operational
60.81.8 km
Aikengall
Wind Onshore · Operational
481.8 km
Crystal Rig Extension II
Wind Onshore · Operational
20.72.1 km
Crystal Rig Wind Farm Phase III
Wind Onshore · Operational
13.82.5 km
Crystal Rig Phase 1
Wind Onshore · Operational
62.52.8 km
Aikengall IIa Community Wind Farm
Wind Onshore · Operational
81.74.1 km

How big is Aikengall II Community Wind Farm Battery?

Aikengall II Community Wind Farm Battery has a recorded installed capacity of 80 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Aikengall II Community Wind Farm Battery?

REPD records the operator as Community Wind Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Aikengall II Community Wind Farm Battery approved and built?

The application was submitted on 2018-01-10. Permission was granted on 2019-01-25, 12 months later. The site became operational on 2021-06-01, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7015.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council