Novarly ParcelRenewable sites

Renewable sitesCrockers Hele

Crockers Hele

Crockers Hele is operational in West Devon with a recorded capacity of 1.3 MW, and has been generating since 2013-09-15.

1.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-09-15
Solar Photovoltaics
Technology
Private Developer
West Devon
Authority
England

Planning and build timeline

Application submitted2012-11-26
Permission granted2013-02-13
3 months after submission
Operational2013-09-15
7 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Devon’s record on solar

West Devon has decided 12 solar farms and approved 83%, taking a median of 3.2 months. See every solar farm decision in West Devon

Other built sites within 15 km

SiteMWDistance
Hillsmoor Solar Farm
Solar Photovoltaics · Operational
1.23.5 km
Willsland Solar farm
Solar Photovoltaics · Operational
3.23.8 km
Beaford Brook Solar Park
Solar Photovoltaics · Operational
5.29.7 km
Southcombe Farm
Solar Photovoltaics · Operational
1.29.7 km
Dunsland Cross Wind Farm
Wind Onshore · Operational
7.512.2 km
Week Farm Solar Park
Solar Photovoltaics · Operational
3.312.3 km
Deep Moor Landfill Site
Solar Photovoltaics · Operational
214 km
Deep Moor Gas to Energy
Landfill Gas · Operational
214.5 km

How big is Crockers Hele?

Crockers Hele has a recorded installed capacity of 1.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Crockers Hele?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Crockers Hele approved and built?

The application was submitted on 2012-11-26. Permission was granted on 2013-02-13, 3 months later. The site became operational on 2013-09-15, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1729.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council