Renewable sites › Deep Moor Gas to Energy
Deep Moor Gas to Energy
Deep Moor Gas to Energy is operational in Torridge with a recorded capacity of 2 MW, and has been generating since 2000-01-13.
Planning and build timeline
| Application submitted | 1998-02-04 |
| Permission granted | 1998-06-12 4 months after submission |
| Operational | 2000-01-13 19 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Deep Moor Landfill Site Solar Photovoltaics · Operational | 2 | 0.5 km |
Darracott Moor Wind Onshore · Operational | 2.6 | 1.4 km |
Knockworthy Farm Solar Photovoltaics · Operational | 3.5 | 2.2 km |
Week Farm Solar Park Solar Photovoltaics · Operational | 3.3 | 2.7 km |
Cleave Farm Solar Park Solar Photovoltaics · Operational | 4.7 | 4.6 km |
Gammaton Moor Solar farm Solar Photovoltaics · Under Construction | 32 | 4.8 km |
Beaford Brook Solar Park Solar Photovoltaics · Operational | 5.2 | 7.1 km |
Chubb Road - Solar Photovoltaic Solar Photovoltaics · Operational | 0.15 | 7.9 km |
How big is Deep Moor Gas to Energy?
Deep Moor Gas to Energy has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Deep Moor Gas to Energy?
REPD records the operator as DEVON WASTE MANAGEMENT LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Deep Moor Gas to Energy approved and built?
The application was submitted on 1998-02-04. Permission was granted on 1998-06-12, 4 months later. The site became operational on 2000-01-13, 19 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 609.