Aberarder Wind Farm

Aberarder Wind Farm is under construction in Highland with a recorded capacity of 49.9 MW.

49.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Scottish & Southern Energy
Highland
Authority
Scotland

Planning and build timeline

Application submitted2015-03-03
Permission granted2017-04-07
25 months after submission
Operationalnot recorded

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Dunmaglass Wind Farm
Wind Onshore · Operational
941 km
Corriegarth
Wind Onshore · Operational
69.510.3 km
Glen Kyllachy Wind Farm
Wind Onshore · Operational
48.511.8 km
Farr Wind Farm
Wind Onshore · Operational
9212 km
Inverfarigaig
Small Hydro · Operational
413.1 km
River E Hydro Scheme
Small Hydro · Operational
313.5 km

How big is Aberarder Wind Farm?

Aberarder Wind Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Aberarder Wind Farm?

REPD records the operator as Scottish & Southern Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Aberarder Wind Farm approved and built?

The application was submitted on 2015-03-03. Permission was granted on 2017-04-07, 25 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3371.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council