Novarly ParcelRenewable sites

Renewable sitesAberarder Wind Farm

Aberarder Wind Farm

Aberarder Wind Farm is a 49.9 MW onshore wind farm under construction in Highland. Planning permission was granted on 7 April 2017, 25 months after submission. Operator of record: Scottish & Southern Energy.

49.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Scottish & Southern Energy
Highland
Authority
Scotland

Planning and build timeline

Application submitted3 March 2015
Permission granted7 April 2017
25 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Aberarder Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
941 km
Wind Onshore · Operational
69.510.3 km
Wind Onshore · Operational
48.511.8 km
Wind Onshore · Operational
9212 km
Small Hydro · Operational
413.1 km
Small Hydro · Operational
313.5 km

How big is Aberarder Wind Farm?

Aberarder Wind Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Aberarder Wind Farm?

REPD records the operator as Scottish & Southern Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Aberarder Wind Farm approved and built?

The application was submitted on 3 March 2015. Permission was granted on 7 April 2017, 25 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3371.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode