Renewable sites › Altaveedan Wind Farm
Altaveedan Wind Farm
Altaveedan Wind Farm is an operational 17.9 MW onshore wind farm in Causeway Coast and Glens, generating since 24 April 2017. Planning permission was granted on 28 October 2013, 35 months after submission. Operator of record: NTR PLC.
Planning and build timeline
| Application submitted | 3 December 2010 |
| Permission granted | 28 October 2013 35 months after submission |
| Operational | 24 April 2017 42 months after consent |
Screening a site of your own?
Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Altaveedan Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 2.5 | 4.7 km |
Wind Onshore · Operational | 5 | 4.9 km |
Wind Onshore · Operational | 25 | 7.5 km |
Wind Onshore · Operational | 12 | 9.6 km |
Wind Onshore · Operational | 2.3 | 12.9 km |
Wind Onshore · Operational | 6.9 | 12.9 km |
How big is Altaveedan Wind Farm?
Altaveedan Wind Farm has a recorded installed capacity of 17.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Altaveedan Wind Farm?
REPD records the operator as NTR PLC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Altaveedan Wind Farm approved and built?
The application was submitted on 3 December 2010. Permission was granted on 28 October 2013, 35 months later. The site became operational on 24 April 2017, 42 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3850.