Renewable sitesAltaveedan Wind Farm

Altaveedan Wind Farm

Altaveedan Wind Farm is an operational 17.9 MW onshore wind farm in Causeway Coast and Glens, generating since 24 April 2017. Planning permission was granted on 28 October 2013, 35 months after submission. Operator of record: NTR PLC.

17.9 MW
Capacity
as recorded in REPD
Operational
Status
since 24 April 2017
Wind Onshore
Technology
NTR PLC
Causeway Coast and Glens
Authority
Northern Ireland

Planning and build timeline

Application submitted3 December 2010
Permission granted28 October 2013
35 months after submission
Operational24 April 2017
42 months after consent

Screening a site of your own?

RedlineUK · £39

Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Altaveedan Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Causeway Coast and Glens’s record on onshore wind

Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.54.7 km
Wind Onshore · Operational
54.9 km
Wind Onshore · Operational
257.5 km
Wind Onshore · Operational
129.6 km
Wind Onshore · Operational
2.312.9 km
Wind Onshore · Operational
6.912.9 km

How big is Altaveedan Wind Farm?

Altaveedan Wind Farm has a recorded installed capacity of 17.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Altaveedan Wind Farm?

REPD records the operator as NTR PLC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Altaveedan Wind Farm approved and built?

The application was submitted on 3 December 2010. Permission was granted on 28 October 2013, 35 months later. The site became operational on 24 April 2017, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3850.