Renewable sites › Altaveedan Wind Farm
Altaveedan Wind Farm
Altaveedan Wind Farm is operational in Causeway Coast and Glens with a recorded capacity of 17.9 MW, and has been generating since 2017-04-24.
Planning and build timeline
| Application submitted | 2010-12-03 |
| Permission granted | 2013-10-28 35 months after submission |
| Operational | 2017-04-24 42 months after consent |
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Corkey Wind Farm Extension Wind Onshore · Operational | 2.5 | 4.7 km |
Corkey Wind Farm Wind Onshore · Operational | 5 | 4.9 km |
Gruig Wind Farm Wind Onshore · Operational | 25 | 7.5 km |
Cloonty Wind Farm Wind Onshore · Operational | 12 | 9.6 km |
Glenbuck Wind Onshore · Operational | 2.3 | 12.9 km |
Glenbuck Wind Onshore · Operational | 6.9 | 12.9 km |
How big is Altaveedan Wind Farm?
Altaveedan Wind Farm has a recorded installed capacity of 17.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Altaveedan Wind Farm?
REPD records the operator as NTR PLC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Altaveedan Wind Farm approved and built?
The application was submitted on 2010-12-03. Permission was granted on 2013-10-28, 35 months later. The site became operational on 2017-04-24, 42 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3850.