Novarly ParcelRenewable sites

Renewable sitesCompton Bassett Landfill

Compton Bassett Landfill

Compton Bassett Landfill is an operational 2 MW landfill gas site in Wiltshire, generating since 1 May 2002. Planning permission was granted on 30 July 1999, 3 months after submission. Operator of record: HILLS MINERALS & WASTE LTD.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 May 2002
Landfill Gas
Technology
HILLS MINERALS & WASTE LTD
Wiltshire
Authority
England

Planning and build timeline

Application submitted16 April 1999
Permission granted30 July 1999
3 months after submission
Operational1 May 2002
33 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Wiltshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Compton Bassett Landfill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
3.50.4 km
Solar Photovoltaics · Operational
9.61.7 km
Anaerobic Digestion · Operational
1.56.8 km
Solar Photovoltaics · Operational
1.37.4 km
Solar Photovoltaics · Operational
69.87.6 km
Solar Photovoltaics · Operational
510.6 km
Solar Photovoltaics · Operational
49.610.9 km
Solar Photovoltaics · Operational
511.1 km

How big is Compton Bassett Landfill?

Compton Bassett Landfill has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Compton Bassett Landfill?

REPD records the operator as HILLS MINERALS & WASTE LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Compton Bassett Landfill approved and built?

The application was submitted on 16 April 1999. Permission was granted on 30 July 1999, 3 months later. The site became operational on 1 May 2002, 33 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 588.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode