Rock Farm / Goldborough Farm (Rookwood) is operational in Wiltshire with a recorded capacity of 5 MW, and has been generating since 2015-03-02.
Planning and build timeline
| Application submitted | 2013-12-20 |
| Permission granted | 2014-07-07 7 months after submission |
| Operational | 2015-03-02 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Wiltshire’s record on solar
Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wickfield Farm Solar Photovoltaics · Operational | 5 | 2.5 km |
Spittleborough Farm Solar Photovoltaics · Operational | 12 | 3 km |
Wroughton Airfield Solar Park Solar Photovoltaics · Operational | 41 | 4.8 km |
Swindon Energy Plant (Park Grounds) Advanced Conversion Technologies · Under Construction | 6 | 5.1 km |
Building ONE Solar Photovoltaics · Under Construction | 1.2 | 5.6 km |
Common Farm Solar Photovoltaics · Operational | 4.8 | 5.6 km |
Mannington Battery Storage Plant Battery · Operational | 49.9 | 5.9 km |
Lower Basset Down Farm Solar Photovoltaics · Operational | 10.5 | 6.2 km |
How big is Rock Farm / Goldborough Farm (Rookwood)?
Rock Farm / Goldborough Farm (Rookwood) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rock Farm / Goldborough Farm (Rookwood)?
REPD records the operator as Good Energy Generation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rock Farm / Goldborough Farm (Rookwood) approved and built?
The application was submitted on 2013-12-20. Permission was granted on 2014-07-07, 7 months later. The site became operational on 2015-03-02, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1834.