Renewable sitesChineham ERF

Chineham ERF

Chineham ERF is operational in Basingstoke and Deane with a recorded capacity of 8 MW, and has been generating since 2002-11-01.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 2002-11-01
EfW Incineration
Technology
Veolia
Basingstoke and Deane
Authority
England

Planning and build timeline

Application submitted1998-10-01
Permission granted1999-11-17
14 months after submission
Operational2002-11-01
35 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Basingstoke Sewage Treatment Works
Anaerobic Digestion · Operational
1.20.2 km
Minchens Lane Battery Storage Facility
Battery · Operational
1004.8 km
Hill End Farm
Solar Photovoltaics · Operational
2.85.6 km
Bunkers Hill Farm - Solar farm & Battery stations
Solar Photovoltaics · Under Construction
49.95.7 km
Bunkers Hill Farm - Solar farm & Battery stations
Battery · Under Construction
5.7 km
Berry Court Solar Farm - energy storage
Battery · Operational
16.3 km
Berry Court Farm
Solar Photovoltaics · Operational
4.26.6 km
Kiln Fields Solar Farm
Solar Photovoltaics · Under Construction
17.876.6 km

How big is Chineham ERF?

Chineham ERF has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chineham ERF?

REPD records the operator as Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chineham ERF approved and built?

The application was submitted on 1998-10-01. Permission was granted on 1999-11-17, 14 months later. The site became operational on 2002-11-01, 35 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 834.