Celcon Blocks Ltd
Celcon Blocks Ltd is operational in East Riding of Yorkshire with a recorded capacity of 2 MW, and has been generating since 2016-04-15.
Planning and build timeline
| Application submitted | 2009-08-04 |
| Permission granted | 2012-10-17 38 months after submission |
| Operational | 2016-04-15 42 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Riding of Yorkshire’s record on onshore wind
East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pollington Solar Farm Solar Photovoltaics · Operational | 5 | 0.6 km |
Land at Pollington Airfield Solar Photovoltaics · Operational | 5 | 1.2 km |
Croda Chemicals Europe Wind Onshore · Operational | 3 | 5.1 km |
Askern Colliery solar farm Solar Photovoltaics · Operational | 5 | 8 km |
Sudforth Lane (Kellingley Solar Farm) Solar Photovoltaics · Operational | 5 | 8.2 km |
Drax Biomass Power Station - Unit 1 Biomass (co-firing) · Operational | 645 | 9 km |
Drax Biomass Power Station - Unit 2 Biomass (dedicated) · Operational | 645 | 9 km |
Drax Biomass Power Station - Unit 3 Biomass (dedicated) · Operational | 645 | 9 km |
How big is Celcon Blocks Ltd?
Celcon Blocks Ltd has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Celcon Blocks Ltd?
REPD records the operator as Ecotricity / Next Generation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Celcon Blocks Ltd approved and built?
The application was submitted on 2009-08-04. Permission was granted on 2012-10-17, 38 months later. The site became operational on 2016-04-15, 42 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2695.