Land at Pollington Airfield is operational in East Riding of Yorkshire with a recorded capacity of 5 MW, and has been generating since 2015-12-21.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-21
Solar Photovoltaics
Technology
Lightsource Renewable Energy
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted2015-05-15
Permission granted2015-07-24
2 months after submission
Operational2015-12-21
5 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on solar

East Riding of Yorkshire has decided 57 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Celcon Blocks Ltd
Wind Onshore · Operational
21.2 km
Pollington Solar Farm
Solar Photovoltaics · Operational
51.6 km
Croda Chemicals Europe
Wind Onshore · Operational
34 km
Drax Biomass Power Station - Unit 2
Biomass (dedicated) · Operational
6458.5 km
Drax Biomass Power Station - Unit 1
Biomass (co-firing) · Operational
6458.5 km
Drax Biomass Power Station - Unit 3
Biomass (dedicated) · Operational
6458.5 km
Drax Biomass Power Station - Unit 4
Biomass (dedicated) · Operational
6458.5 km
Askern Colliery solar farm
Solar Photovoltaics · Operational
58.5 km

How big is Land at Pollington Airfield?

Land at Pollington Airfield has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Pollington Airfield?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Pollington Airfield approved and built?

The application was submitted on 2015-05-15. Permission was granted on 2015-07-24, 2 months later. The site became operational on 2015-12-21, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5322.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council