Land at Pollington Airfield
Land at Pollington Airfield is operational in East Riding of Yorkshire with a recorded capacity of 5 MW, and has been generating since 2015-12-21.
Planning and build timeline
| Application submitted | 2015-05-15 |
| Permission granted | 2015-07-24 2 months after submission |
| Operational | 2015-12-21 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Riding of Yorkshire’s record on solar
East Riding of Yorkshire has decided 57 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in East Riding of Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Celcon Blocks Ltd Wind Onshore · Operational | 2 | 1.2 km |
Pollington Solar Farm Solar Photovoltaics · Operational | 5 | 1.6 km |
Croda Chemicals Europe Wind Onshore · Operational | 3 | 4 km |
Drax Biomass Power Station - Unit 2 Biomass (dedicated) · Operational | 645 | 8.5 km |
Drax Biomass Power Station - Unit 1 Biomass (co-firing) · Operational | 645 | 8.5 km |
Drax Biomass Power Station - Unit 3 Biomass (dedicated) · Operational | 645 | 8.5 km |
Drax Biomass Power Station - Unit 4 Biomass (dedicated) · Operational | 645 | 8.5 km |
Askern Colliery solar farm Solar Photovoltaics · Operational | 5 | 8.5 km |
How big is Land at Pollington Airfield?
Land at Pollington Airfield has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Pollington Airfield?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Pollington Airfield approved and built?
The application was submitted on 2015-05-15. Permission was granted on 2015-07-24, 2 months later. The site became operational on 2015-12-21, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5322.