Bowbeat Emly Bank / Rough Side is an operational 31.2 MW onshore wind farm in Scottish Borders, generating since 15 September 2002. Planning permission was granted on 14 August 2000, 5 months after submission. Operator of record: PowerGen and Natural Power.

31.2 MW
Capacity
as recorded in REPD
Operational
Status
since 15 September 2002
Wind Onshore
Technology
PowerGen and Natural Power
Scottish Borders
Authority
Scotland

Planning and build timeline

Application submitted23 March 2000
Permission granted14 August 2000
5 months after submission
Operational15 September 2002
25 months after consent

Screening a site of your own?

RedlineUK · £39

Scottish Borders approves 56% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bowbeat Emly Bank / Rough Side’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Borders’s record on onshore wind

Scottish Borders has decided 41 onshore wind schemes and approved 56%, taking a median of 13.6 months. See every onshore wind scheme decision in Scottish Borders

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
67.4 km
Wind Onshore · Operational
27.613.9 km

How big is Bowbeat Emly Bank / Rough Side?

Bowbeat Emly Bank / Rough Side has a recorded installed capacity of 31.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bowbeat Emly Bank / Rough Side?

REPD records the operator as PowerGen and Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bowbeat Emly Bank / Rough Side approved and built?

The application was submitted on 23 March 2000. Permission was granted on 14 August 2000, 5 months later. The site became operational on 15 September 2002, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3299.