Calow Green Farm
Calow Green Farm is operational in North East Derbyshire with a recorded capacity of 20 MW, and has been generating since 2019-10-01.
Planning and build timeline
| Application submitted | 2018-09-10 |
| Permission granted | 2020-03-31 19 months after submission |
| Operational | 2019-10-01 |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North East Derbyshire’s record on battery storage
North East Derbyshire has decided 10 battery storage schemes and approved 60%, taking a median of 3.3 months. See every battery storage scheme decision in North East Derbyshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land To The East Of Back Lane Solar Photovoltaics · Operational | 5 | 0.6 km |
Land north of Temple Normanton Solar Photovoltaics · Operational | 4.9 | 1.6 km |
Cherry Tree Farm Solar Photovoltaics · Operational | 5 | 2.7 km |
Arkwright Solar Farm Solar Photovoltaics · Operational | 8 | 3.5 km |
Inkersall Road, Staveley - Solar Photovoltaic Farm And Battery Storage Battery · Operational | — | 4.8 km |
Inkersall Road, Staveley - Solar Photovoltaic Farm And Battery Storage Solar Photovoltaics · Operational | 31 | 4.8 km |
Glapwell Landfill Gas · Operational | 1.2 | 4.9 km |
Glapwell Power Landfill Gas · Operational | 2 | 5.1 km |
How big is Calow Green Farm?
Calow Green Farm has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Calow Green Farm?
REPD records the operator as Arlington Energy (formerly Enso Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Calow Green Farm approved and built?
The application was submitted on 2018-09-10. Permission was granted on 2020-03-31, 19 months later. The site became operational on 2019-10-01.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7140.