Renewable sites › Land north of Temple Normanton
Land north of Temple Normanton
Land north of Temple Normanton is operational in North East Derbyshire with a recorded capacity of 4.9 MW, and has been generating since 2016-03-31.
Planning and build timeline
| Application submitted | 2014-08-14 |
| Permission granted | 2014-12-17 4 months after submission |
| Operational | 2016-03-31 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North East Derbyshire’s record on solar
North East Derbyshire has decided 19 solar farms and approved 95%, taking a median of 3.5 months. See every solar farm decision in North East Derbyshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Calow Green Farm Battery · Operational | 20 | 1.6 km |
Land To The East Of Back Lane Solar Photovoltaics · Operational | 5 | 2.2 km |
Cherry Tree Farm Solar Photovoltaics · Operational | 5 | 3.9 km |
Glapwell Landfill Gas · Operational | 1.2 | 4.3 km |
Glapwell Power Landfill Gas · Operational | 2 | 4.3 km |
Arkwright Solar Farm Solar Photovoltaics · Operational | 8 | 4.9 km |
Inkersall Road, Staveley - Solar Photovoltaic Farm And Battery Storage Solar Photovoltaics · Operational | 31 | 6.2 km |
Inkersall Road, Staveley - Solar Photovoltaic Farm And Battery Storage Battery · Operational | — | 6.2 km |
How big is Land north of Temple Normanton?
Land north of Temple Normanton has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land north of Temple Normanton?
REPD records the operator as NESF (formerly Lark Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land north of Temple Normanton approved and built?
The application was submitted on 2014-08-14. Permission was granted on 2014-12-17, 4 months later. The site became operational on 2016-03-31, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2162.