Burton Wold Wind Farm South
Burton Wold Wind Farm South is operational in North Northamptonshire with a recorded capacity of 7.5 MW, and has been generating since 2017-04-24.
Planning and build timeline
| Application submitted | 2015-02-18 |
| Permission granted | 2015-03-27 1 months after submission |
| Operational | 2017-04-24 25 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Northamptonshire’s record on onshore wind
North Northamptonshire has decided 9 onshore wind schemes and approved 67%, taking a median of 4.7 months. See every onshore wind scheme decision in North Northamptonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Burton Wold Wind Farm - Northern Extension Wind Onshore · Operational | 14.4 | 0.9 km |
Burton Wold Windfarm Wind Onshore · Operational | 20 | 1.2 km |
Cranford Landfill Gas · Operational | 1.1 | 2.9 km |
Sidegate Lane Landfill Gas · Operational | 2.4 | 3.4 km |
Sidegate Lane Landfill Site Landfill Gas · Operational | 1.3 | 3.4 km |
Little Irchester, Higham Road Solar Farm Solar Photovoltaics · Operational | 4.6 | 7.1 km |
London Road, Irchester - Solar Farm Solar Photovoltaics · Operational | 26 | 8.4 km |
Wellingborough Solar Farm Solar Photovoltaics · Operational | 8.5 | 8.4 km |
How big is Burton Wold Wind Farm South?
Burton Wold Wind Farm South has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Burton Wold Wind Farm South?
REPD records the operator as Infinergy/ Muirhall Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Burton Wold Wind Farm South approved and built?
The application was submitted on 2015-02-18. Permission was granted on 2015-03-27, 1 months later. The site became operational on 2017-04-24, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5277.