Renewable sitesLondon Road, Irchester - Solar Farm

London Road, Irchester - Solar Farm

London Road, Irchester - Solar Farm is operational in North Northamptonshire with a recorded capacity of 26 MW.

26 MW
Capacity
as recorded in REPD
Operational
Status
no operational date
Solar Photovoltaics
Technology
Atrato Onsite Energy
North Northamptonshire
Authority
England

Planning and build timeline

Application submitted2022-05-26
Permission granted2022-11-08
5 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Northamptonshire’s record on solar

North Northamptonshire has decided 41 solar farms and approved 98%, taking a median of 2 months. See every solar farm decision in North Northamptonshire

Other built sites within 15 km

SiteMWDistance
Little Irchester, Higham Road Solar Farm
Solar Photovoltaics · Operational
4.61.6 km
Wellingborough Solar Farm
Solar Photovoltaics · Operational
8.51.6 km
Sidegate Lane Landfill Site
Landfill Gas · Operational
1.35 km
Sidegate Lane
Landfill Gas · Operational
2.45 km
Glebe Farm Solar Energy Park
Solar Photovoltaics · Operational
156.3 km
Airfield Farm (Podington)
Wind Onshore · Operational
8.66.3 km
Odell Glebe Solar Farm
Solar Photovoltaics · Operational
16.87.3 km
Westwood AD Plant (Farm AD)
Anaerobic Digestion · Operational
27.6 km

How big is London Road, Irchester - Solar Farm?

London Road, Irchester - Solar Farm has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates London Road, Irchester - Solar Farm?

REPD records the operator as Atrato Onsite Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was London Road, Irchester - Solar Farm approved and built?

The application was submitted on 2022-05-26. Permission was granted on 2022-11-08, 5 months later. REPD does not record an operational date.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11423.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council