Renewable sites › Bryn Blaen Wind Farm
Bryn Blaen Wind Farm
Bryn Blaen Wind Farm is operational in Powys with a recorded capacity of 13.8 MW, and has been generating since 2019-01-01.
Planning and build timeline
| Application submitted | 2014-12-04 |
| Permission granted | 2016-08-23 21 months after submission |
| Operational | 2019-01-01 28 months after consent |
Powys’s record on onshore wind
Powys has decided 22 onshore wind schemes and approved 68%, taking a median of 36.8 months. See every onshore wind scheme decision in Powys →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bryn titli Windfarm Wind Onshore · Operational | 9.9 | 6.1 km |
Bryn Du Wind Onshore · Operational | 16.4 | 7.7 km |
Cefn Croes Wind Farm Wind Onshore · Operational | 58.5 | 10.8 km |
Llandinam Windfarm Wind Onshore · Operational | 31 | 11.4 km |
Carno 'A' Wind Farm Wind Onshore · Operational | 16.8 | 13.7 km |
Carno 'A'and 'B' Wind Farm, (Extension) Wind Onshore · Operational | 15.6 | 13.7 km |
Elan Valley Hydro Scheme Small Hydro · Operational | 2.9 | 14 km |
Carno 'B' Wind Farm Wind Onshore · Operational | 16.8 | 14.5 km |
How big is Bryn Blaen Wind Farm?
Bryn Blaen Wind Farm has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bryn Blaen Wind Farm?
REPD records the operator as Njord Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bryn Blaen Wind Farm approved and built?
The application was submitted on 2014-12-04. Permission was granted on 2016-08-23, 21 months later. The site became operational on 2019-01-01, 28 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2873.