Bryn Blaen Wind Farm

Bryn Blaen Wind Farm is an operational 13.8 MW onshore wind farm in Powys, generating since 1 January 2019. Planning permission was granted on 23 August 2016, 21 months after submission. Operator of record: Njord Energy.

13.8 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 2019
Wind Onshore
Technology
Njord Energy
Powys
Authority
Wales

Planning and build timeline

Application submitted4 December 2014
Permission granted23 August 2016
21 months after submission
Operational1 January 2019
28 months after consent

Screening a site of your own?

RedlineUK · £39

Powys approves 68% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bryn Blaen Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Powys’s record on onshore wind

Powys has decided 22 onshore wind schemes and approved 68%, taking a median of 36.8 months. See every onshore wind scheme decision in Powys

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
9.96.1 km
Wind Onshore · Operational
16.47.7 km
Wind Onshore · Operational
58.510.8 km
Wind Onshore · Operational
3111.4 km
Wind Onshore · Operational
16.813.7 km
Wind Onshore · Operational
15.613.7 km
Small Hydro · Operational
2.914 km
Wind Onshore · Operational
16.814.5 km

How big is Bryn Blaen Wind Farm?

Bryn Blaen Wind Farm has a recorded installed capacity of 13.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bryn Blaen Wind Farm?

REPD records the operator as Njord Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bryn Blaen Wind Farm approved and built?

The application was submitted on 4 December 2014. Permission was granted on 23 August 2016, 21 months later. The site became operational on 1 January 2019, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2873.