Novarly ParcelRenewable sites

Renewable sitesBryn titli Windfarm

Bryn titli Windfarm

Bryn titli Windfarm is an operational 9.9 MW onshore wind farm in Powys, generating since 1 June 1994. Planning permission was granted on 9 August 1993, 5 months after submission. Operator of record: Innogy.

9.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 June 1994
Wind Onshore
Technology
Innogy
Powys
Authority
Wales

Planning and build timeline

Application submitted12 March 1993
Permission granted9 August 1993
5 months after submission
Operational1 June 1994
10 months after consent

Screening a site of your own?

RedlineUK · £39

Powys approves 68% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bryn titli Windfarm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Powys’s record on onshore wind

Powys has decided 22 onshore wind schemes and approved 68%, taking a median of 36.8 months. See every onshore wind scheme decision in Powys

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
13.86.1 km
Small Hydro · Operational
2.98.7 km
Small Hydro · Operational
1.19.1 km
Wind Onshore · Operational
16.411 km
Wind Onshore · Operational
3112.4 km
Wind Onshore · Operational
58.513.3 km

How big is Bryn titli Windfarm?

Bryn titli Windfarm has a recorded installed capacity of 9.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bryn titli Windfarm?

REPD records the operator as Innogy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bryn titli Windfarm approved and built?

The application was submitted on 12 March 1993. Permission was granted on 9 August 1993, 5 months later. The site became operational on 1 June 1994, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3015.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode