Renewable sites › Cefn Croes Wind Farm
Cefn Croes Wind Farm
Cefn Croes Wind Farm is an operational 58.5 MW onshore wind farm in Ceredigion, generating since 25 January 2005. Planning permission was granted on 10 December 2001, 17 months after submission. Operator of record: Renewable Development Company Ltd, KENTECH Ltd.
Planning and build timeline
| Application submitted | 24 July 2000 |
| Permission granted | 10 December 2001 17 months after submission |
| Operational | 25 January 2005 38 months after consent |
Screening a site of your own?
Ceredigion approves 83% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Cefn Croes Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Ceredigion’s record on onshore wind
Ceredigion has decided 6 onshore wind schemes and approved 83%, taking a median of 14.9 months. See every onshore wind scheme decision in Ceredigion →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 16.4 | 3.2 km |
Wind Onshore · Operational | 2.4 | 8.6 km |
Wind Onshore · Operational | 13.8 | 10.8 km |
Wind Onshore · Operational | 9.9 | 13.3 km |
How big is Cefn Croes Wind Farm?
Cefn Croes Wind Farm has a recorded installed capacity of 58.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cefn Croes Wind Farm?
REPD records the operator as Renewable Development Company Ltd, KENTECH Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cefn Croes Wind Farm approved and built?
The application was submitted on 24 July 2000. Permission was granted on 10 December 2001, 17 months later. The site became operational on 25 January 2005, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2563.
Novarly Parcel · official public data, read properly · parcel.novarly.com