Carno 'B' Wind Farm is operational in Powys with a recorded capacity of 16.8 MW, and has been generating since 1996-10-01.

16.8 MW
Capacity
as recorded in REPD
Operational
Status
since 1996-10-01
Wind Onshore
Technology
RWE npower
Powys
Authority
Wales

Planning and build timeline

Application submitted1993-12-30
Permission granted1995-08-18
20 months after submission
Operational1996-10-01
13 months after consent

Powys’s record on onshore wind

Powys has decided 22 onshore wind schemes and approved 68%, taking a median of 36.8 months. See every onshore wind scheme decision in Powys

Other built sites within 15 km

SiteMWDistance
Carno 'A' Wind Farm
Wind Onshore · Operational
16.82.1 km
Carno 'A'and 'B' Wind Farm, (Extension)
Wind Onshore · Operational
15.62.1 km
Cemmaes 'C' Wind Farm
Wind Onshore · Operational
15.311 km
Tirgwynt
Wind Onshore · Operational
24.611.1 km
Mynydd Clogau Wind Farm
Wind Onshore · Operational
14.512.6 km
Cemmaes 'B' Wind Farm
Wind Onshore · Operational
3.412.8 km
Bryn Blaen Wind Farm
Wind Onshore · Operational
13.814.5 km

How big is Carno 'B' Wind Farm?

Carno 'B' Wind Farm has a recorded installed capacity of 16.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Carno 'B' Wind Farm?

REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Carno 'B' Wind Farm approved and built?

The application was submitted on 1993-12-30. Permission was granted on 1995-08-18, 20 months later. The site became operational on 1996-10-01, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2564.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council