Llandinam Windfarm is an operational 31 MW onshore wind farm in Powys, generating since 1 January 1993. REPD does not record the planning grant date. Operator of record: CELTPOWER LTD.

31 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 1993
Wind Onshore
Technology
CELTPOWER LTD
Powys
Authority
Wales

Planning and build timeline

Application submittednot recorded
Permission grantednot recorded
Operational1 January 1993

Screening a site of your own?

RedlineUK · £39

Powys approves 68% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Llandinam Windfarm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Powys’s record on onshore wind

Powys has decided 22 onshore wind schemes and approved 68%, taking a median of 36.8 months. See every onshore wind scheme decision in Powys

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
3410.5 km
Wind Onshore · Operational
13.811.4 km
Wind Onshore · Operational
9.912.4 km

How big is Llandinam Windfarm?

Llandinam Windfarm has a recorded installed capacity of 31 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Llandinam Windfarm?

REPD records the operator as CELTPOWER LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Llandinam Windfarm approved and built?

REPD does not record a submission date. REPD does not record a grant date. The site became operational on 1 January 1993.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3057.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode