Renewable sites › Broom Hill Farm
Broom Hill Farm
Broom Hill Farm is operational in County Durham with a recorded capacity of 8 MW, and has been generating since 2009-02-16.
Planning and build timeline
| Application submitted | 2006-02-02 |
| Permission granted | 2006-12-08 10 months after submission |
| Operational | 2009-02-16 26 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
County Durham’s record on onshore wind
County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
High Hedley Hope 2 (Extension) Wind Onshore · Operational | 5.2 | 1.5 km |
Hedley Hope Wind Onshore · Operational | 2.4 | 1.5 km |
West Durham Wind Farm Wind Onshore · Operational | 24 | 3.8 km |
Tow Law Wind Farm Wind Onshore · Operational | 2.6 | 4.3 km |
Langley Moor Wind Onshore · Operational | 8 | 9.8 km |
Green Croft Solar Farm Solar Photovoltaics · Operational | 5 | 10.9 km |
Greencroft Estate Turbines Wind Onshore · Operational | 4 | 11.1 km |
Hownsgill Industrial Park Solar Photovoltaics · Under Construction | 5 | 11.2 km |
How big is Broom Hill Farm?
Broom Hill Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Broom Hill Farm?
REPD records the operator as EDF Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Broom Hill Farm approved and built?
The application was submitted on 2006-02-02. Permission was granted on 2006-12-08, 10 months later. The site became operational on 2009-02-16, 26 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2983.