Novarly ParcelRenewable sites

Renewable sitesWest Durham Wind Farm

West Durham Wind Farm

West Durham Wind Farm is operational in County Durham with a recorded capacity of 24 MW, and has been generating since 2009-05-01.

24 MW
Capacity
as recorded in REPD
Operational
Status
since 2009-05-01
Wind Onshore
Technology
ESBI
County Durham
Authority
England

Planning and build timeline

Application submitted2005-01-01
Permission granted2005-12-01
11 months after submission
Operational2009-05-01
41 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on onshore wind

County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham

Other built sites within 15 km

SiteMWDistance
Tow Law Wind Farm
Wind Onshore · Operational
2.60.5 km
High Hedley Hope 2 (Extension)
Wind Onshore · Operational
5.23.7 km
Hedley Hope
Wind Onshore · Operational
2.43.7 km
Broom Hill Farm
Wind Onshore · Operational
83.8 km
Hownsgill Industrial Park
Solar Photovoltaics · Under Construction
58.6 km
Land Adjacent to Thomas Swan and Co Ltd.
Anaerobic Digestion · Operational
110.1 km
Derwentside Environmental Testing Servs Limited - Solar pv panels
Solar Photovoltaics · Operational
0.3810.5 km
Greencroft Estate Turbines
Wind Onshore · Operational
410.5 km

How big is West Durham Wind Farm?

West Durham Wind Farm has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates West Durham Wind Farm?

REPD records the operator as ESBI. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was West Durham Wind Farm approved and built?

The application was submitted on 2005-01-01. Permission was granted on 2005-12-01, 11 months later. The site became operational on 2009-05-01, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2955.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council