Novarly ParcelRenewable sites

Renewable sitesTow Law Wind Farm

Tow Law Wind Farm

Tow Law Wind Farm is operational in County Durham with a recorded capacity of 2.6 MW, and has been generating since 2001-12-30.

2.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2001-12-30
Wind Onshore
Technology
RWE npower
County Durham
Authority
England

Planning and build timeline

Application submitted1999-07-27
Permission granted2000-06-07
10 months after submission
Operational2001-12-30
19 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on onshore wind

County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham

Other built sites within 15 km

SiteMWDistance
West Durham Wind Farm
Wind Onshore · Operational
240.5 km
Hedley Hope
Wind Onshore · Operational
2.44.2 km
High Hedley Hope 2 (Extension)
Wind Onshore · Operational
5.24.2 km
Broom Hill Farm
Wind Onshore · Operational
84.3 km
Hownsgill Industrial Park
Solar Photovoltaics · Under Construction
58.5 km
Land Adjacent to Thomas Swan and Co Ltd.
Anaerobic Digestion · Operational
110.1 km
Derwentside Environmental Testing Servs Limited - Solar pv panels
Solar Photovoltaics · Operational
0.3810.4 km
Greencroft Estate Turbines
Wind Onshore · Operational
410.7 km

How big is Tow Law Wind Farm?

Tow Law Wind Farm has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tow Law Wind Farm?

REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tow Law Wind Farm approved and built?

The application was submitted on 1999-07-27. Permission was granted on 2000-06-07, 10 months later. The site became operational on 2001-12-30, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2586.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council