Renewable sites › Boxted Airfield
Boxted Airfield
Boxted Airfield is operational in Colchester with a recorded capacity of 18.8 MW, and has been generating since 2015-03-19.
Planning and build timeline
| Application submitted | 2014-06-16 |
| Permission granted | 2014-09-15 3 months after submission |
| Operational | 2015-03-19 6 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Colchester’s record on solar
Colchester has decided 19 solar farms and approved 95%, taking a median of 3 months. See every solar farm decision in Colchester →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Chancery Farm (Ardleigh) Solar Photovoltaics · Operational | 11.9 | 5.7 km |
Colchester STW Sewage Sludge Digestion · Operational | 1.2 | 7.5 km |
Blue Gates Farm Wind Onshore · Operational | 1.5 | 10.3 km |
Bluegates Solar Park Solar Photovoltaics · Operational | 10.5 | 10.5 km |
Bellhouse Pit Landfill Scheme Landfill Gas · Operational | 2.7 | 10.7 km |
Bellhouse South Landfill Gas · Operational | 3.9 | 11.2 km |
Babergh Home Solar Scheme Solar Photovoltaics · Operational | 2.8 | 11.8 km |
Layer Farm - Solar Farm Solar Photovoltaics · Operational | 49 | 12.1 km |
How big is Boxted Airfield?
Boxted Airfield has a recorded installed capacity of 18.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Boxted Airfield?
REPD records the operator as NextEnergy Solar Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Boxted Airfield approved and built?
The application was submitted on 2014-06-16. Permission was granted on 2014-09-15, 3 months later. The site became operational on 2015-03-19, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2143.