Novarly ParcelRenewable sites

Renewable sitesBlue Gates Farm

Blue Gates Farm

Blue Gates Farm is an operational 1.5 MW onshore wind farm in Tendring, generating since 1 March 2010. Planning permission was granted on 11 September 2009, 3 months after submission. Operator of record: M H Leyland Ltd.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2010
Wind Onshore
Technology
M H Leyland Ltd
Tendring
Authority
England

Planning and build timeline

Application submitted5 June 2009
Permission granted11 September 2009
3 months after submission
Operational1 March 2010
6 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Tendring: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Blue Gates Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
10.50.3 km
Sewage Sludge Digestion · Operational
1.25.1 km
Solar Photovoltaics · Operational
11.95.3 km
Solar Photovoltaics · Operational
21.37.2 km
Solar Photovoltaics · Operational
137.3 km
Wind Onshore · Operational
10.39.5 km
Solar Photovoltaics · Operational
18.79.9 km
Solar Photovoltaics · Operational
18.810.3 km

How big is Blue Gates Farm?

Blue Gates Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Blue Gates Farm?

REPD records the operator as M H Leyland Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Blue Gates Farm approved and built?

The application was submitted on 5 June 2009. Permission was granted on 11 September 2009, 3 months later. The site became operational on 1 March 2010, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2694.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode