Renewable sites › Bishop�s Waltham Solar Farm
Bishop�s Waltham Solar Farm
Bishop�s Waltham Solar Farm is operational in Winchester with a recorded capacity of 12 MW, and has been generating since 2017-02-17.
Planning and build timeline
| Application submitted | 2015-04-17 |
| Permission granted | 2015-08-07 4 months after submission |
| Operational | 2017-02-17 18 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Nutrient-neutrality catchment — Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Winchester’s record on solar
Winchester has decided 24 solar farms and approved 100%, taking a median of 2.9 months. See every solar farm decision in Winchester →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Forest Farm Solar Photovoltaics · Operational | 3 | 0.4 km |
Raglington Farm Solar Photovoltaics · Operational | 5.8 | 3.4 km |
Fairoak Landfill Landfill Gas · Operational | 1.5 | 5.6 km |
Titchfield Lane Battery · Under Construction | 49 | 6.8 km |
Chalcroft Solar Park Solar Photovoltaics · Operational | 6.3 | 7 km |
Concorde Way, Segensworth - Solar Panels Solar Photovoltaics · Under Construction | 1.04 | 8.6 km |
Netley Landfill Solar Solar Photovoltaics · Operational | 12 | 10.6 km |
Netley Landfill Site, Hampshire (Extension) Landfill Gas · Operational | 1.2 | 11 km |
How big is Bishop�s Waltham Solar Farm?
Bishop�s Waltham Solar Farm has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bishop�s Waltham Solar Farm?
REPD records the operator as Solafields U/Bishop's Waltham Renewables Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bishop�s Waltham Solar Farm approved and built?
The application was submitted on 2015-04-17. Permission was granted on 2015-08-07, 4 months later. The site became operational on 2017-02-17, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1325.
Novarly Parcel · official public data, read properly · parcel.novarly.com