Renewable sites › Birmingham Bio-Power Plant
Birmingham Bio-Power Plant
Birmingham Bio-Power Plant is operational in Birmingham with a recorded capacity of 10.3 MW, and has been generating since 2016-06-15.
Planning and build timeline
| Application submitted | 2012-08-13 |
| Permission granted | 2012-10-26 2 months after submission |
| Operational | 2016-06-15 44 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tyseley ERF EfW Incineration · Operational | 30 | 0.4 km |
Minsworth Sewage Treatment Works Sewage Sludge Digestion · Operational | 9.7 | 9.8 km |
Packington Generation Plant Phase 3 Landfill Gas · Operational | 8.5 | 10.3 km |
Coleshill STW (Waste AD) Anaerobic Digestion · Operational | 2.4 | 10.9 km |
Kelvin Energy Recovery Facility EfW Incineration · Under Construction | 47 | 11.7 km |
Kelvin Energy Recovery Facility EfW Incineration · Under Construction | 47 | 11.7 km |
Hams Hall - Battery Energy Storage System Battery · Under Construction | 400 | 11.9 km |
DPD Distribution Centre Solar Photovoltaics · Operational | 1 | 12.4 km |
How big is Birmingham Bio-Power Plant?
Birmingham Bio-Power Plant has a recorded installed capacity of 10.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Birmingham Bio-Power Plant?
REPD records the operator as Birmingham Bio-Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Birmingham Bio-Power Plant approved and built?
The application was submitted on 2012-08-13. Permission was granted on 2012-10-26, 2 months later. The site became operational on 2016-06-15, 44 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1010.